The Project

Manor Lane is a £27.5M residential development by Weston Homes in Feltham, Hounslow.

The new apartments at Manor Lane will range in size from 535 sq ft to 1020 sq ft and will all benefit from Weston Homes signature features. An all inclusive specification that includes integrated applicances, and quartz stone worktops in the kitchen, state of the art bathrooms with Smart technology and luxury flooring fitted throughout.

In total, 104 apartments are being developed comprising of 1, 2 and 3 bed residential units. Additionally to this, underground parking have been created along with access and landscaping.

The Challenge

Due to the scale of the project and the tight program for installation, a bulk call off order would be required. The contractor needed reassurance that the supplier would be able to fulfill the regular orders for delivery in full without balances.

As the project is in a residential area, there are strict delivery restrictions imposed by the developer to ensure swift deliveries of products.

The client required premium quality of products to match the high standards of the build.

Brymec were the selected supplier of multiple products required for the project. 

1

Product Selection

With the £12million stock holding and the stock promise guarantee for the top 2,000 products, Brymec were able to consistently supply the plumbing and mechanical products required for the project.

Brymec supplied complete integrated system components that were desired by the contractor. Systems supplied included:

1

Steel Tube & Fittings

The striking installation on the project has 3 miles worth of our Steel Tube. Let's put that into perspective:

Thats 47 football pitch lengths,

The height of 60 80m cranes,

The Brymec Distribution Centre stacked 459 times!

950 of our Brymec Vans bumper to bumper! 

Gas Press Systems

Gas Copper Fittings

3
4

Site Supports & Fixings

Slotted Channel

Square Plates

Hexagon Nuts

Insulated Pipe Clamps

The Result

Our dedicated team were able to tackle the challenges the project had.

The call off schedule was managed seamlessly with consistant next day delivery of all tube and fittings on the pre-determined bulk call off order. The rhythm of timely deliveries, expertly handled by our FORS accredited drivers enabled the team to meet the install program without delays.

All orders delivered had no balances due to the £12M stock holding and Brymec stock promise.

Having inspected the supplied materials and products, the client was extremely happy of the high quality products and had no issues.

Testimonial

Project Manager, Daniel O'Brien, states: Brymec has been really easy to deal with. You order it and you have the confidence and assurance that it will come next day. The drivers are really helpful and don't just sit and watch. The whole service offering has helped us to keep the project on track.

The product has been great! No problems on any of the product and is easy to work with.